2025 - 2027 / Pisco — Peru

POA II – Pisco Operation Assurance (Phase 2)

The POA II project contemplates the integral execution under EPC modality of a set of strategic improvements aimed at strengthening the operational security, reliability and continuity of the Pisco Natural Gas Liquid Fractionation Plant (PFLGN), Marine Terminal and Land Dispatch Plant, located in the region ICA. The scope integrates critical equipment, security instrumented systems and automation solutions applied to the three installations.

470.000
Man-hours Worked
234
Personnel Peak People
545
Instruments Installed
331
Mounted Valves

Technical complexity and safe operational continuity

The scope of the project considers the implementation of multidisciplinary modifications in critical process systems, fire protection, fire detection & Gas, safety instrumented systems and operational adjustments aimed at reducing the risk profile of the facilities under ALARP criteria (AS low as reasonably practicable).
The execution of the project presents a high level of technical and operational complexity due to its development within facilities in continuous operation, requiring integrated planning, strict control of interference and permanent coordination between disciplines to guarantee the operational continuity and safety of the facilities.

Execution on site

11,400+

Inches Welding Diameters

390+

Tons of scaffolds required

850+

m³ of excavations and concrete cast

53+

Tons of assembly of structures

52.100

Meters of instrumentation wiring installed

164

Tons of spool mounted

Main components of the project

Improvements in fire and foam systems of the process plant

Improvements in coverage and performance of the Fire & Gas system

Implementation of fireproof protection

Integration of IEC 61511 Instrumented Security Instrumented Systems

Operational Excellence

0

Occupational Diseases

0

Environmental events

770+

SSMA inspections carried out

2,600+

SSMA Training Man-Hours

Project Chronology

Contract start

September 2025

Contract Termination

February 2027

Execution Time

412 days